Construction Updates

Currently Underway


March 9, 2018

Post Oak Boulevard – North Segment Construction / 610 to San Felipe

Paving at intersection of Post Oak Boulevard and Uptown Park Boulevard is now completed

Driveway work continues from 777 Post Oak Boulevard north to 610

Installation of sidewalks on the southbound side continues

Communication duct banks and primary electrical continues to be installed in the median

Post Oak Boulevard – Middle Segment Construction / San Felipe to Westheimer 

Paving continues from BLVD Place moving south in the northbound lanes

Installation of water lines and storm sewer will continue in the northbound lanes from Lynn

Lane moving south toward Westheimer 

Installation of trees from Ambassador Way north to San Felipe on the southbound side continues

Installation of sidewalks on the southbound side continues

Water meter vaults will be relocated in various locations along the boulevard

Post Oak Boulevard – South Segment Construction / Westheimer to Richmond 

Installation of new live oak trees south of West Alabama will continue

Continue concrete paving in the northbound lanes from West Alabama to Westheimer

Continue waterline crossing at Westheimer on east side of Post Oak Boulevard

Continue electrical conduits and lighting foundations northbound and southbound Fairdale to Parkview, and northbound Parkview to West Alabama in preparations for sidewalk installation

Crosswalk between Dillard’s and The Galleria is now closed

CenterPoint, AT&T and other contractors continue the adjustment and relocation work in the area.

All work subject to change based on weather conditions and utility conflicts.

If you have questions, please contact us at

View all Construction Updates



December – Pedestrian environment prototype is completed. Wider sidewalks, pedestrian lights and trees are added to an area on Post Oak Boulevard to aid in planning the construction.


November – Modifications on the arches at Four Oaks Place and Willie G’s began.


August – The first iconic ring was removed from the intersection of Post Oak Boulevard and Uptown Park Boulevard for refurbishment. Watch Video


June – Tree Preservation Plan is implemented. First tree is removed from the median and relocated to a new, permanent location along Post Oak Boulevard.


City Council unanimously approved budget and 5-year CIP

TxDOT approved West Loop Dedicated Bus Lanes

Groundbreaking of The Boulevard


environmental clearance granted by Federal Transit Administration granted


$62M grant approved by Houston-Galveston Area Council

revised Project Plan approved by City Council


Referendum approved transit on Post Oak Boulevard


Project Plan Approved by City Council